The projects, costing P98 million, is funded by the Countrywide Development Fund (CDF) of House Speaker Jose de Venecia Jr.
Engineer Fidel Ginez, assistant regional director of the Department of Public Works and Highways and concurrent project manager of the Agno Flood Control Project based in Tumana, Rosales town, said the first project involves the construction of a P53-million closure dike in Barangay Amag-bagan, Sison town.
Work on the closure dike began last July 25. It is expected to be finished on Jan. 30, 2004.
The second project involves the construction of a P45-million earth dike in Barangay Embarcadero-Salaan, Mangaldan town and in Patalan-Lungos, San Fabian town.
The dike project commenced on July 9. It is also expected to be completed on Jan. 30, 2004.
Both dike projects are now 75-percent complete. Eva Visperas