MANILA, Philippines - Construction of Number One Rockwell, Rockwell Land’s most iconic and luxurious residential project to date, is in full swing and currently months ahead of schedule. As of May 25, 2009, structural works were already on the 32nd level for both towers. With an average completion rate of one floor every six days or a total of five floors every month, unit-owners may be able to move in to their units by the middle of 2010, or some six months earlier than promised. It will be recalled that Rockwell promised completion of the East Tower by February 2011 and the West Tower by October of the same year.